Helonic is an AI construction drawing analysis platform for people check areas of refuge during plan review. The two-way phone, the clear floor space, and the stair landing have to fit on the enlarged stair plan
An area of refuge passes review when the enlarged stair plan shows one 30 by 48 inch wheelchair space for every 200 occupants served, placed outside the required egress width, next to a two-way communication device, on a stair at least 48 inches wide between handrails. Helonic checks that the refuge fits on the enlarged plan. IBC Sections 1009.3 and 1009.6 set those numbers. The miss is a refuge that is hatched on the life safety plan but does not fit once the stair, the door swing, and the handrails are drawn.
IBC Section 1009 requires accessible means of egress from accessible spaces. On floors above or below the level of exit discharge, an exit stair used as an accessible means of egress has to be at least 48 inches wide between handrails. It also has to include an area of refuge on an enlarged landing, or be reached from an area of refuge or a horizontal exit.
Buildings sprinklered throughout under NFPA 13 or 13R are exempt from both the 48 inch width and the area of refuge in most cases. Check the sprinkler status on the code plan before you look for a refuge.
Section 1009.6.3 requires one wheelchair space, 30 by 48 inches, for every 200 occupants or portion of 200. The count is based on the occupant load of the refuge and the areas it serves. The spaces can't reduce the required egress width or capacity, and reaching any one space can't require passing through more than one other space.
| Occupants served | Wheelchair spaces |
|---|---|
| 1 to 200 | 1 |
| 201 to 400 | 2 |
| 401 to 600 | 3 |
| 601 to 800 | 4 |
The refuge is separated from the rest of the floor by a smoke barrier, or it sits behind a horizontal exit, unless it is inside the stair enclosure itself. Occupant load math is in how to calculate occupant load.
Most refuges sit on an enlarged landing inside the stair. That landing already has to hold the stair width, the door swing, and the handrail extensions. The wheelchair space goes on top of all of that, outside the path people take down the stair. These are the conflicts that show up on the enlarged plan:
The communication device has its own page: area of refuge two-way communication covers where it goes and what it calls. Stair geometry is in stair design requirements.
Drawing the required space on the plan, rather than trusting a label, is a habit that applies across how to review construction drawings.
Draw the 30 by 48 inch rectangle on the enlarged plan yourself. A hatch labeled area of refuge says nothing about whether the space fits.
Helonic reads the code plan, the enlarged stair plans, the electrical plans, and the signage drawings together. It flags a refuge whose stair is under 48 inches between handrails, a wheelchair space inside the egress width, a door swing over the space, and a refuge with no communication device. The accessibility checks cite the sheet and the grid for each finding.
Findings are decision support. The architect decides what changes. For how this review fits a project, see AI for construction drawings.
Practitioner insight
“The hatch says area of refuge, and the enlarged plan has a 44 inch stair, a 36 inch door swinging onto the landing, and nowhere left to park a wheelchair.”
Common finding in accessibility and egress drawing review.
Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.
How this page was researched: Requirements were checked against IBC 2021 Sections 1009.3 and 1009.6 for accessible means of egress stairs and area of refuge size and separation. The two-way communication system is covered on a separate page so the two do not share a query.
Last reviewed by Manas Gandhi · October 8, 2026
Related references for accessible means of egress review.
The phone at the refuge, which this page does not repeat.
Stair width, landings, and handrails.
Accessible routes that lead to the refuge.
The outdoor version at the level of exit discharge.
Accessibility requirements across the drawing set.
A systematic approach to catching drawing errors before construction.