Helonic is an AI construction drawing analysis platform for people check smokeproof stair vestibules during plan review. The vestibule depth and the door swings have to leave the required width on the enlarged stair plan
A smokeproof stair vestibule passes review when the enlarged stair plan shows a vestibule at least 44 inches wide and 72 inches long in the direction of travel, and neither door swing cuts the egress width in the vestibule or on the stair landing below what the code allows. Helonic checks the vestibule with both doors drawn open. IBC Section 909.20 sets the vestibule size and its 2-hour separation. The miss is a vestibule that measures right wall to wall but stops working once the doors are drawn.
IBC Section 909.20 requires access to a smokeproof stair through a vestibule or an open exterior balcony. The vestibule is at least as wide as the corridor that leads to it, never less than 44 inches, and at least 72 inches long in the direction of egress travel.
The enclosure is separated from the rest of the building by 2-hour fire barriers, and the vestibule is separated from the stair by 2-hour fire barriers too. Ventilation is natural, through an exterior opening of at least 16 square feet facing a yard, court, or public way at least 20 feet wide, or mechanical, with supply of at least one air change per minute and exhaust at 150 percent of supply.
A fully sprinklered building can skip the vestibule by pressurizing the stair. That option is covered in stair pressurization requirements.
The vestibule is part of the means of egress, so the door rules in Chapter 10 apply inside it. IBC Section 1005.7.1 lets a door reduce the required width by no more than half during its swing, and a fully open door can project no more than 7 inches into the required width. Section 1011.6 applies the same limits to the stair landing.
Both doors swing in the direction of egress. The door from the floor swings into the vestibule, and the door from the vestibule swings onto the stair landing. That puts one leaf in each of the two spaces the code sizes most tightly.
| Door | Swings into | What to check |
|---|---|---|
| Floor to vestibule | Vestibule | The leaf leaves at least half the required width during its swing and does not collide with the second door. |
| Vestibule to stair | Stair landing | The leaf leaves at least half the required landing width during its swing and projects 7 inches or less when fully open. |
| Both doors | Both spaces | Each door carries the rating its wall needs and closes automatically. |
Door ratings and closers live on the door schedule. Stair width and landing geometry are in stair design requirements.
The same method of drawing doors open before signing off on a space works for every egress room. It is part of how to review construction drawings.
Compare the enlarged plan and the floor plan at the same grid lines. When the stair core moves late in design, the floor plan gets updated and the enlarged plan keeps the old vestibule.
Helonic compares the enlarged stair plans, the floor plans, the wall types, and the door schedule for each smokeproof stair. It flags a vestibule shorter than 72 inches, a door swing that cuts the landing, a 1-hour wall where 2-hour is required, and a mechanical vestibule with no air. The egress compliance checks cite the sheet and grid for each finding.
Findings are decision support. The architect decides what changes. For how this review fits a project, see AI for construction drawings.
Practitioner insight
“The vestibule is 6 feet on the floor plan and 5 foot 8 on the enlarged plan because the stair moved four inches during design development and only one drawing got updated.”
Common finding in high-rise egress drawing review.
Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.
How this page was researched: Requirements were checked against IBC 2021 Section 909.20 for smokeproof enclosures and Sections 1005.7.1 and 1011.6 for door encroachment in the means of egress and on stair landings.
Last reviewed by Manas Gandhi · October 7, 2026
Related references for stair and egress review.
The pressurized alternative to a vestibule.
Stair width, landings, and handrails.
How required width is calculated.
A full egress review on a drawing set.
Fire barriers and opening protectives.
A systematic approach to catching drawing errors before construction.