Helonic is an AI construction drawing analysis platform for people check horizontal exits during plan review. The fire wall, the swinging doors, and the refuge capacity on each side have to agree
A horizontal exit passes review when the wall carries at least a 2-hour rating and runs continuously, the doors swing the way people will travel through them, and the refuge area on each side holds its own occupants plus the people coming through from the other side. Helonic checks all three against the code plan. IBC Section 1026 sets all three. The common miss is a life safety plan that labels a horizontal exit while the wall type, the door schedule, or the occupant load math says otherwise.
IBC Section 1026 treats a horizontal exit as a wall you pass through to reach safety on the same floor. The separation is a fire wall or a fire barrier rated at least 2 hours. It runs continuously from exterior wall to exterior wall, so the floor is split into two areas, and it extends through every level unless the floor assemblies carry at least a 2-hour rating with no unprotected openings.
A horizontal exit can't be the only exit from any part of a floor. In most occupancies it can provide no more than half of the required exits and half of the required exit width. Group I-2 and I-3 occupancies get higher allowances.
Doors in the wall are fire door assemblies that are self-closing, or automatic-closing on smoke detection. For how ratings carry through walls and openings, see the fire rating guide.
Section 1026.4 sizes the refuge area on the receiving side for its own occupants plus the people arriving from the other side. The arriving number is the lesser of the adjoining area's occupant load and the capacity of the horizontal exit doors. The refuge area is at least 3 square feet of net floor area per occupant in most occupancies, with larger figures for Group I-2 and I-3.
Each side still needs its own exits sized for its own occupants, not counting the people coming through. Occupant load math is in how to calculate occupant load. Here is a worked example for a wall used from both sides, assuming the doors can carry each side's full load:
| Side | Own occupants | Arriving from other side | Total | Minimum refuge area at 3 sq ft |
|---|---|---|---|---|
| Side A | 300 | 200 | 500 | 1,500 sq ft |
| Side B | 200 | 300 | 500 | 1,500 sq ft |
The refuge area also has to be public space or space occupied by the same tenant. Counting another tenant's locked suite as refuge does not work.
Doors serving 50 or more occupants swing in the direction of egress travel under IBC Section 1010.1.2.1. When a horizontal exit is used from both sides, a single door can only swing one way. The usual answer is a pair of doors, each leaf swinging away from one side, so everyone pushes in the direction they are going.
If the doors are held open, they need to close on smoke detection. The fire alarm drawings should show the release, and the door schedule should show the hold-open and closer hardware.
Following one wall through every discipline is the core of how to review construction drawings.
If the code plan uses the wall as an exit from both sides, do the refuge math for both sides. Reviewers often check only the side people flee toward.
Helonic follows each horizontal exit across the code plan, the wall types, the door schedule, and the fire alarm drawings. It flags a wall rated below 2 hours, a single door in a two-way wall, a refuge area too small for the arriving load, and a code plan that leans on horizontal exits for more than half its exits. The egress compliance checks cite the sheet and grid for each finding.
Findings are decision support. The architect decides what changes. For how this review fits a project, see AI for construction drawings.
Practitioner insight
“I see the horizontal exit symbol on the life safety plan and a single door swinging east on the door schedule. The west side is using it too, so half the people are pulling a door against the crowd.”
Common finding in hospital and large-floor-plate egress review.
Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.
How this page was researched: Requirements were checked against IBC 2021 Section 1026 for horizontal exits, its refuge area provisions, and Section 1010.1.2.1 for door swing direction.
Last reviewed by Manas Gandhi · October 7, 2026
Related references for egress and life safety review.
Where horizontal exits are shown and labeled.
Exits, exit access, and exit discharge.
The numbers behind the refuge area.
Another rated exit component that runs horizontally.
Common egress errors on drawing sets.
A systematic approach to catching drawing errors before construction.