Helonic is an AI construction drawing analysis platform for architects and engineers answering plan check comments on a permit resubmittal. Plan check comments come back on almost every permit set, and how you answer them decides whether the second submittal is the last one. This Helonic guide covers what plan check is, how to structure the comment-response letter, how to cloud and delta revisions, and why sets end up in a third round.
To respond to plan check comments, answer every comment in a numbered response letter that quotes the comment, states the change, and names the sheet and detail where it appears. Cloud each revision and tag it with that round's delta number. Helonic compares the revised set to the prior one and flags changes that were not clouded.
Plan check is the building department's review of construction documents against the adopted building, fire, energy, and zoning codes before it issues a permit. IBC Section 107.2.1 requires the documents to show the work conforms to code "as determined by the building official," and the plans examiner is the person making that call. When something is missing or noncompliant, the examiner sends back a correction list.
The applicant revises the set and resubmits, and the cycle repeats until every reviewer approves. California jurisdictions usually call this plan check; elsewhere it is often plan review. Requirements vary by city, and Helonic's plan check by city pages cover the adopted codes and local amendments in each one.
Honolulu's Department of Planning and Permitting reported an average of 3.4 plan review cycles across 17 residential permits that did not use its AI pre-screen. Seattle's 2026 CivCheck evaluation report puts the historical median for middle housing at 3.72 correction cycles and 161 calendar days to pass plan review.
Each cycle in Seattle takes about a month of calendar time, by the same report. Getting out in two rounds instead of three or four is mostly a matter of how the first response is written and checked.
The response letter is a checklist for the examiner. A good one lets them find every change in seconds. Build it this way:
Here is what three entries look like when they are written to be checked:
| Comment | Response | Location |
|---|---|---|
| B-4. Provide the occupant load for every room. IBC 107.2.3. | Occupant loads added to every room on the life-safety plans. Code analysis table and plumbing fixture count updated to the new totals. | G-002; LS-101 to LS-104; delta 1 |
| B-9. Corridor rating at Level 2 does not match wall type W3. | Corridor walls changed to W3A (1-hour). Door schedule updated to 20-minute doors at Level 2 corridor. | A-102; A-601 wall types; A-701 door schedule; delta 1 |
| F-2. Show fire separation distance at the north wall openings. | Fire separation distance dimensioned to the lot line. Opening area recalculated and shown in the table. | A-201; G-003 opening table; delta 1 |
Compare that with "Revised per comment." That response gives the examiner nothing to check, so they recheck the whole sheet and anything nearby.
Clouds show the examiner where the set changed, and deltas show which round each change belongs to. Hawaii County's cloud and delta memo is a clear version of the rule most cities follow:
Hawaii County rejects resubmittals at intake that skip the cloud and delta format or the response letter. Milpitas keeps earlier clouds on the sheets and gives each round its own delta, and only clouded changes carrying that delta count as part of an approved revision. An unclouded change is an unreviewed change.
Format matters as much as content at intake. Seattle reviews only complete plan sets, not loose sheets, and rejects uploads that are missing sheets or correction responses. Danville treats a resubmittal without a response letter as incomplete.
A third round usually traces back to how round two was answered. These are the patterns that cause it:
The second item on that list has a long tail. A comment can be closed with the city while the condition is still wrong somewhere else in the set, which then reaches the field. That problem, and how to reconcile it before construction, is covered in code comments become field problems.
Before upload, check the revised drawings and ignore the letter. Read each comment, open the sheet you cited, and confirm the change is there and clouded. Then search the set for every other place the changed element appears: the door number, the wall type, the occupant load, the equipment tag.
Helonic does the comparison step on the PDFs. Revision comparison tracks what changed between the prior set and the revised one and flags modifications that were not clouded. A fresh review of the revised set with code compliance checking catches fixes that created a new conflict, with a page location for each finding.
The fewer comments you get in round one, the less of this there is. The pre-submittal plan review checklist covers that pass. For the AI tools some cities now run before intake, see city AI plan review vs applicant AI plan check and what the Honolulu and Seattle AI permit pilots measured. For the broader category, read what AI plan review is and AI plan check on the building department side.
Practitioner insight
“The third round almost never comes from the comment. It comes from the fix. We widen a corridor for egress and the toilet room next to it loses its turning circle, or we change a wall type on the plan and the door schedule still says the old rating. Now we search the whole set for everything a change touches before anyone writes the response.”
Source: Conversations with project architects and permit coordinators managing resubmittals on commercial and multifamily projects, synthesized from Helonic's design-side interviews, Q3 2026.
Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.
How this page was researched: Reviewed against resubmittal requirements published by Seattle SDCI, the County of Hawaii Building Division, Milpitas, and Danville, and against plan review cycle data from Honolulu DPP and Seattle's 2026 CivCheck evaluation report.
Last reviewed by Manas Gandhi · October 2026
More on getting a permit set through plan check in fewer rounds.
The discipline-by-discipline pass that keeps round one short.
Making sure approved responses reach the construction set.
Corrections and review cycles from two city AI pre-screening reports.
Which AI tools cities buy, which ones design teams buy, and what each checks.