Helonic is an AI construction drawing analysis platform for teams researching templates during drawing review. Free change order template for construction: cost breakdown, OH&P, contract sum before and after, time extension, and signatures. Download the CSV.
A change order template is a fill-in form that records a signed change to the construction contract: what changed, why, what it costs, how many days it adds, and who agreed to it. The template below covers the same ground as an AIA G701 change order, adds a line-item cost breakdown, and includes a separate change order request (PCO or COR) form for the pricing stage.
A complete construction change order form has five parts: identification (CO number, project, contract date), a description of the change with drawing and spec references, the reason or origin (owner request, design error, unforeseen condition, RFI), a cost breakdown with markup, and the contract sum and contract time before and after. It is valid only once the owner, architect, and contractor sign.
Every field below exists so someone reading the change order a year later can rebuild the decision without the email chain. The example column follows one change on a three-story medical office building: a rated shaft wall that the architect added after an RFI exposed a missing fire-rated enclosure.
| Field | What to enter | Example |
|---|---|---|
| CO number | Sequential number, never reused. Note the PCO or COR it came from. | CO-014 (from COR-031) |
| Project | Project name, address, and job number. | Riverside Medical Office Building, Job 2418 |
| Owner, architect, contractor | Firm name and address for each party. | Riverside Health LLC / Marlow Architects / Keystone Builders |
| Contract date | Date of the original owner-contractor agreement. | March 4, 2026 |
| CO date | Date the change order is issued for signature. | October 22, 2026 |
| Description of change | What changes and where, with sheet, detail, and spec section references. Attach backup. | Add 2-hour rated shaft wall at Level 3 corridor per ASI-007, sheets A-203 and A-501 detail 4, spec 09 21 16 |
| Reason / origin | Owner request, design error or omission, unforeseen condition, or code requirement. Cite the RFI, ASI, or CCD. | Design omission. RFI-052 response issued as ASI-007 |
| Labor | Hours times rate, by trade. | 64 hr x $92 = $5,888 |
| Material | Quantities and unit costs, or attached quote. | $3,140 (board, studs, firestopping) |
| Equipment | Rental or owned rates and duration. | Scissor lift, 1 week: $640 |
| Subcontractor | Sub's price with their own breakdown attached. | Drywall sub: $11,860 |
| Markup / OH&P | Overhead and profit percentages the contract allows on self-performed and sub work. | 10% on own work ($967), 5% on sub ($593) |
| Bond and insurance | Only if the contract allows it as a separate line. | 1% ($231) |
| Total change amount | Sum of all lines above. Show credits as negative. | $23,319 |
| Contract sum before | Original contract sum, net of previous change orders, and the sum prior to this CO. | $18,450,000 + $412,300 = $18,862,300 |
| Contract sum after | Prior sum plus or minus this change. | $18,885,619 |
| Time extension (days) | Calendar or working days, per the contract. Write 0 if none. | 3 calendar days |
| New substantial completion date | Adjusted date after this change. | June 15, 2027 (was June 12, 2027) |
| Signatures | Owner, architect, and contractor: name, title, date. | Signed by all three, Oct 24 to Oct 29, 2026 |
The cost breakdown is where most change orders stall, because the owner can't tell what they're paying for. Here is the same CO-014 priced line by line, with markup applied the way most contracts separate self-performed work from subcontracted work.
| Cost item | Basis | Amount |
|---|---|---|
| Labor (GC carpenters) | 64 hr x $92/hr | $5,888 |
| Material | Type X board, 6 in. studs, firestop sealant | $3,140 |
| Equipment | Scissor lift, 1 week | $640 |
| Subtotal, self-performed | $9,668 | |
| OH&P on self-performed | 10% of $9,668 | $967 |
| Subcontractor (drywall) | Sub quote dated Oct 15, 2026, backup attached | $11,860 |
| Markup on sub | 5% of $11,860 | $593 |
| Subtotal | $23,088 | |
| Bond and insurance | 1% of $23,088 | $231 |
| Total, CO-014 | $23,319 |
Download the change order template (CSV, opens in Excel or Google Sheets). The header row holds every field above and the second row holds the CO-014 example, so you can overwrite it or keep it as a reference.
If your contract is on AIA documents, the executed change order should still be the AIA G701 form or whatever form the contract names. Use this template as the backup sheet that travels with it, and as a running log of every change on the job.
A change order request is the contractor's priced proposal before anyone signs a change order. Teams call it a PCO (potential change order), COR (change order request), or change proposal, and one CO often bundles several of them.
The request needs fewer signatures and more status tracking. These are the fields worth keeping in a change order request template:
| Field | What to enter | Example |
|---|---|---|
| COR number | Sequential, separate from CO numbers. | COR-031 |
| Date submitted | Date sent to the owner or architect. | October 3, 2026 |
| Originating document | RFI, ASI, CCD, bulletin, field directive, or owner email. | RFI-052 / ASI-007 |
| Description | Scope change in one or two sentences with sheet references. | Rated shaft wall at L3 corridor, A-203 |
| Pricing method | Lump sum, unit price, time and materials, or not-to-exceed. | Lump sum |
| Proposed amount | Total with breakdown attached. | $23,319 |
| Proposed days | Days requested and the schedule activity affected. | 3 days, activity L3 drywall close-in |
| Response required by | Date the work starts affecting the schedule. | October 17, 2026 |
| Status | Open, under review, revised, approved, rejected, or converted to CO. | Converted to CO-014 |
This page gives you the form. For the process behind it (who issues what, when a construction change directive applies, and how to negotiate), read the construction change order guide. If you're unsure whether an issue should be an RFI, ASI, bulletin, or change order at all, start with RFI vs ASI vs bulletin vs change order.
Most change orders begin as an RFI, so the RFI template in this series uses the same reference style. To compare your totals with typical projects, see the change order cost benchmark.
Helonic doesn't write or price change orders. It works earlier: it reads the full PDF drawing set and flags the cross-discipline conflicts and missing information that later turn into design-error change orders, such as the missing rated enclosure in the example above. The drawing conflict detection page shows what it checks, and the change order prevention guide covers the rest of the prevention workflow.
Milind is the co-founder and CEO of Helonic, where he leads product and go-to-market for AI-powered construction drawing analysis. He works closely with general contractors, project managers, estimators, and owners to understand how drawing quality drives project outcomes - and where AI can reduce RFIs, change orders, and rework. Milind has interviewed hundreds of construction professionals across project delivery roles, from preconstruction estimators at ENR top-400 contractors to facilities directors at institutional owners, and uses those conversations to shape both product direction and the way Helonic talks about the work.
How this page was researched: Field coverage was checked against AIA's published instructions and public sample for G701-2017 Change Order (help.aiacontracts.com and aiacontracts.com, checked November 1, 2026), and against the change and directive provisions in Article 7 of AIA A201-2017. No AIA form text is reproduced; the cost figures are an illustrative example, not benchmark data.
Last reviewed by Milind Sagaram · November 1, 2026