Change Order Template for Construction (Free CSV Download)

Helonic is an AI construction drawing analysis platform for teams researching templates during drawing review. Free change order template for construction: cost breakdown, OH&P, contract sum before and after, time extension, and signatures. Download the CSV.

TemplatesNovember 1, 2026

A change order template is a fill-in form that records a signed change to the construction contract: what changed, why, what it costs, how many days it adds, and who agreed to it. The template below covers the same ground as an AIA G701 change order, adds a line-item cost breakdown, and includes a separate change order request (PCO or COR) form for the pricing stage.

A complete construction change order form has five parts: identification (CO number, project, contract date), a description of the change with drawing and spec references, the reason or origin (owner request, design error, unforeseen condition, RFI), a cost breakdown with markup, and the contract sum and contract time before and after. It is valid only once the owner, architect, and contractor sign.

What fields does a construction change order form need?

Every field below exists so someone reading the change order a year later can rebuild the decision without the email chain. The example column follows one change on a three-story medical office building: a rated shaft wall that the architect added after an RFI exposed a missing fire-rated enclosure.

Change order template fields
FieldWhat to enterExample
CO numberSequential number, never reused. Note the PCO or COR it came from.CO-014 (from COR-031)
ProjectProject name, address, and job number.Riverside Medical Office Building, Job 2418
Owner, architect, contractorFirm name and address for each party.Riverside Health LLC / Marlow Architects / Keystone Builders
Contract dateDate of the original owner-contractor agreement.March 4, 2026
CO dateDate the change order is issued for signature.October 22, 2026
Description of changeWhat changes and where, with sheet, detail, and spec section references. Attach backup.Add 2-hour rated shaft wall at Level 3 corridor per ASI-007, sheets A-203 and A-501 detail 4, spec 09 21 16
Reason / originOwner request, design error or omission, unforeseen condition, or code requirement. Cite the RFI, ASI, or CCD.Design omission. RFI-052 response issued as ASI-007
LaborHours times rate, by trade.64 hr x $92 = $5,888
MaterialQuantities and unit costs, or attached quote.$3,140 (board, studs, firestopping)
EquipmentRental or owned rates and duration.Scissor lift, 1 week: $640
SubcontractorSub's price with their own breakdown attached.Drywall sub: $11,860
Markup / OH&POverhead and profit percentages the contract allows on self-performed and sub work.10% on own work ($967), 5% on sub ($593)
Bond and insuranceOnly if the contract allows it as a separate line.1% ($231)
Total change amountSum of all lines above. Show credits as negative.$23,319
Contract sum beforeOriginal contract sum, net of previous change orders, and the sum prior to this CO.$18,450,000 + $412,300 = $18,862,300
Contract sum afterPrior sum plus or minus this change.$18,885,619
Time extension (days)Calendar or working days, per the contract. Write 0 if none.3 calendar days
New substantial completion dateAdjusted date after this change.June 15, 2027 (was June 12, 2027)
SignaturesOwner, architect, and contractor: name, title, date.Signed by all three, Oct 24 to Oct 29, 2026

What does a filled-in change order cost breakdown look like?

The cost breakdown is where most change orders stall, because the owner can't tell what they're paying for. Here is the same CO-014 priced line by line, with markup applied the way most contracts separate self-performed work from subcontracted work.

Example: CO-014 cost breakdown
Cost itemBasisAmount
Labor (GC carpenters)64 hr x $92/hr$5,888
MaterialType X board, 6 in. studs, firestop sealant$3,140
EquipmentScissor lift, 1 week$640
Subtotal, self-performed$9,668
OH&P on self-performed10% of $9,668$967
Subcontractor (drywall)Sub quote dated Oct 15, 2026, backup attached$11,860
Markup on sub5% of $11,860$593
Subtotal$23,088
Bond and insurance1% of $23,088$231
Total, CO-014$23,319

Download the change order template

Download the change order template (CSV, opens in Excel or Google Sheets). The header row holds every field above and the second row holds the CO-014 example, so you can overwrite it or keep it as a reference.

If your contract is on AIA documents, the executed change order should still be the AIA G701 form or whatever form the contract names. Use this template as the backup sheet that travels with it, and as a running log of every change on the job.

What goes on a change order request (PCO or COR)?

A change order request is the contractor's priced proposal before anyone signs a change order. Teams call it a PCO (potential change order), COR (change order request), or change proposal, and one CO often bundles several of them.

The request needs fewer signatures and more status tracking. These are the fields worth keeping in a change order request template:

Change order request (PCO / COR) template fields
FieldWhat to enterExample
COR numberSequential, separate from CO numbers.COR-031
Date submittedDate sent to the owner or architect.October 3, 2026
Originating documentRFI, ASI, CCD, bulletin, field directive, or owner email.RFI-052 / ASI-007
DescriptionScope change in one or two sentences with sheet references.Rated shaft wall at L3 corridor, A-203
Pricing methodLump sum, unit price, time and materials, or not-to-exceed.Lump sum
Proposed amountTotal with breakdown attached.$23,319
Proposed daysDays requested and the schedule activity affected.3 days, activity L3 drywall close-in
Response required byDate the work starts affecting the schedule.October 17, 2026
StatusOpen, under review, revised, approved, rejected, or converted to CO.Converted to CO-014

How do you use a change order template step by step?

  • Log the change as soon as you know about it. Open a COR the day an RFI answer, ASI, or owner request changes scope, even before pricing.
  • Check the contract's notice clause. Many contracts set a deadline for written notice of a claimed change, and missing it can waive the claim.
  • Write the description with references. Name the sheets, details, and spec sections that changed, and attach the revised drawings or sketch.
  • Price it with backup. Get sub quotes broken into labor, material, and equipment, and apply only the markups the contract allows.
  • Request time separately from money. If the change hits the critical path, show the schedule activity and the days, or write 0.
  • Roll approved CORs into a change order, update the contract sum lines, and collect all three signatures before billing the work.

What are the most common change order mistakes?

  • Lump-sum pricing with no breakdown, which invites a line-by-line dispute.
  • No reason code, so nobody can later tell design errors from owner changes.
  • Leaving the time field blank instead of writing 0, which some teams read as reserving the right to claim days later.
  • Applying markup on markup, such as GC OH&P on top of sub OH&P beyond what the contract allows.
  • Doing the work on a verbal approval and writing the change order after the fact.
  • Contract sum lines that don't reconcile with the previous change order.

How does this template relate to the change order guide?

This page gives you the form. For the process behind it (who issues what, when a construction change directive applies, and how to negotiate), read the construction change order guide. If you're unsure whether an issue should be an RFI, ASI, bulletin, or change order at all, start with RFI vs ASI vs bulletin vs change order.

Most change orders begin as an RFI, so the RFI template in this series uses the same reference style. To compare your totals with typical projects, see the change order cost benchmark.

Where does Helonic fit in the change order process?

Helonic doesn't write or price change orders. It works earlier: it reads the full PDF drawing set and flags the cross-discipline conflicts and missing information that later turn into design-error change orders, such as the missing rated enclosure in the example above. The drawing conflict detection page shows what it checks, and the change order prevention guide covers the rest of the prevention workflow.

Frequently Asked Questions

What should be included in a construction change order?
A change order number, the project and contract date, a description of the change with sheet and spec references, the reason for the change, a cost breakdown with markup, the contract sum before and after, any change in contract time, and signatures from the owner, architect, and contractor.
What is the difference between a change order request and a change order?
A change order request (also called a PCO or COR) is the contractor's proposal for price and time. A change order is the signed contract amendment that results once the owner and contractor agree. One change order can roll up several approved requests.
Can I use this template instead of AIA G701?
If your contract specifies AIA G701 or another form, execute the change on that form. This template works as the cost backup and the running change log. On projects without a required form, it covers the same essential fields.
What markup is allowed on a change order?
Whatever the contract says. Many contracts set separate overhead and profit percentages for self-performed work and for subcontracted work, and some cap bond and insurance as a separate line. Check the changes article and any supplementary conditions before pricing.
Who signs a construction change order?
On AIA-based contracts, the owner, architect, and contractor all sign, and the change order is not valid until they do. Other contract forms may only require the owner and contractor. Subcontract change orders are signed by the GC and the sub.
Should a change order include a time extension?
Every change order should state the change in contract time, even when it is zero days. Writing 0 makes the agreement on time explicit, while a blank field leaves room for a later dispute.
MS

Milind Sagaram

Co-founder & CEO, Helonic

Milind is the co-founder and CEO of Helonic, where he leads product and go-to-market for AI-powered construction drawing analysis. He works closely with general contractors, project managers, estimators, and owners to understand how drawing quality drives project outcomes - and where AI can reduce RFIs, change orders, and rework. Milind has interviewed hundreds of construction professionals across project delivery roles, from preconstruction estimators at ENR top-400 contractors to facilities directors at institutional owners, and uses those conversations to shape both product direction and the way Helonic talks about the work.

Areas of focus
  • Construction project delivery and preconstruction
  • RFI and change order economics
  • Owner and GC workflows for drawing QA/QC
  • Estimating risk and bid-stage scope assessment

How this page was researched: Field coverage was checked against AIA's published instructions and public sample for G701-2017 Change Order (help.aiacontracts.com and aiacontracts.com, checked November 1, 2026), and against the change and directive provisions in Article 7 of AIA A201-2017. No AIA form text is reproduced; the cost figures are an illustrative example, not benchmark data.

Last reviewed by Milind Sagaram · November 1, 2026