HelonicHelonic

Geotechnical reports for construction: boring logs, bearing capacity, and IBC requirements

A reviewer-grade reference for geotechnical reports (also called geotech reports or soil reports) in commercial construction: what each section contains, how to read boring logs, how bearing capacity drives footing design, and what IBC Section 1803 requires for permit submittal.

ReferenceLast reviewed by Manas Gandhi · May 2026

Key Sections of a Geotech Report

A complete geotechnical report for construction includes these sections:

  • Executive Summary, high-level findings and recommendations for foundations
  • Scope and Methodology, where borings were drilled, how deep, testing performed
  • Boring Logs, detailed description of soil at each depth
  • Laboratory Test Results, classification, strength, and compaction data
  • Recommendations, allowable bearing pressure, compaction standards, dewatering notes
  • Conclusions, summary of key findings and limitations

Reading Boring Logs

Boring logs are the core of a geotech report. Each log represents a hole drilled at a specific location. Learn to read them:

Depth Increments

The left side shows depth in feet (sometimes meters). Each horizontal band represents a soil layer. Read from top (0 ft, ground level) down.

Example: "Fill (0 to 2'), Sandy Silt (2 to 8'), Glacial Clay (8 to 25')" tells you that below the surface are three distinct layers.

Soil Descriptions

Soil is described by grain size, color, consistency, and moisture. Example: "Medium dense, brown, fine-grained sand with trace mica." This description tells you:

  • Grain size: Sand (coarse, 0.05 to 2 mm), Silt (fine, 0.002 to 0.05 mm), Clay (very fine, <0.002 mm)
  • Density/consistency: Loose, medium dense, dense, soft, firm, stiff, hard (increases bearing capacity)
  • Water content: Dry, moist, wet (affects compressibility and stability)

SPT N-Values

Standard Penetration Test (SPT) is the most common field test. A weight is dropped down a tube, and resistance is measured. The result is the "N-value", recorded as "blows per foot." Example: N = 15 means 15 hammer blows to drive the sampler 1 foot.

Higher N-values mean denser, stronger soil:

  • N < 5: Very loose/soft. Poor bearing capacity.
  • N = 5 to 10: Loose/soft. Moderate bearing capacity.
  • N = 10 to 30: Medium density/firm. Good bearing capacity.
  • N > 30: Dense/stiff. Excellent bearing capacity.

Groundwater Elevation (GWL)

The boring log shows where water was encountered. Example: "GWL at 6 feet" means the water table is 6 feet below ground level. This is critical:

  • Footings below GWL require waterproofing and drainage design
  • Soil bearing capacity decreases when saturated
  • Excavation may require dewatering (pumping) to keep the hole dry
  • Seasonal variation matters, report notes if GWL was higher or lower during boring

Allowable Bearing Pressure

The geotech engineer recommends an allowable bearing capacity (usually in PSF, pounds per square foot) for each soil layer. This is the maximum load a footing can safely support.

Example from a report: "Glacial clay below 8 feet depth: allowable bearing capacity = 3,000 PSF." The structural engineer uses this value to design footing sizes. If the bearing capacity is low, footings must be larger (and more expensive).

Practical example

Column load = 300 kips (300,000 lbs). Allowable bearing = 3,000 PSF. Footing area required = 300,000 ÷ 3,000 = 100 square feet ≈ 10' × 10' footing. If bearing capacity were only 2,000 PSF, footing would need to be 15' × 15', much more expensive.

The geotechnical report will also specify depth of footing (typically 3 to 4 feet minimum to avoid frost heave and poor surface conditions).

Lateral Earth Pressure for Retaining Walls

If the project includes retaining walls, the geotech report provides lateral earth pressure values. These are used to design wall thickness and reinforcement.

Key values provided:

  • At-rest pressure (K₀): Force exerted on wall with no wall movement. Used for walls that cannot move (e.g., basement walls).
  • Active pressure (Kₐ): Force when wall leans away from soil (typical for cantilever walls). Lower than at-rest.
  • Passive pressure (Kₚ): Resistance provided by soil in front of wall. Used for design of wall toe depth.

The geotech report will state these as coefficients (e.g., Kₐ = 0.35 for a particular soil). The structural engineer multiplies this by soil weight and wall height to calculate the total lateral load.

Compaction Requirements

For fills (areas where soil is added and compacted), the geotech report specifies compaction standards. This is critical for preventing settlement.

Typical specification: "All fill shall be compacted to 95% of maximum dry density (ASTM D698) in 6-inch lifts."

What this means:

  • 95% maximum dry density: Soil is compacted to remove voids. Higher percentage = denser, more stable soil. 95% is standard; 98% is more stringent.
  • ASTM D698: Standard test method (there's also D1557 for heavier equipment; contractor must know which applies).
  • 6-inch lifts: Fill is placed and compacted in 6-inch-thick layers. Helps ensure uniform compaction.
  • Proof rolling: After compaction, heavy equipment (vibratory roller or loaded truck) is driven over the area. If ruts appear, additional compaction is required.

Poor compaction leads to settlement, which can crack slabs and damage structures. This is why geotech inspectors are on site during fill placement.

Groundwater: Seasonal Variation and Dewatering

The groundwater level reported in the geotech investigation represents the level on the day of boring. But groundwater fluctuates with seasons, rainfall, and nearby surface water.

A good geotech report will note:

  • Historical high water table: Highest level anticipated based on seasonal data. Plan excavation and drainage for this level.
  • Seasonal variation: Example: "GWL typically rises 3 to 4 feet in spring due to snowmelt."
  • Dewatering requirements: If excavation extends below GWL, the contractor must pump water to keep the excavation dry. This adds cost and schedule time.

If dewatering is required, the geotech report may recommend a groundwater control system (sumps, wells, or French drains). This should be detailed in the specifications and reflected in site plans.

How Geotech Recommendations Translate to Structural Drawings

The structural engineer uses geotech data to design foundations:

1

Footing Size and Depth

Geotech recommends allowable bearing and minimum depth. Structural engineer calculates footing size based on column loads and specifies in footing schedule on sheet S3.

2

Slab-on-Grade Design

Geotech specifies fill compaction, base course, and if floor is above or below GWL. Structural engineer shows slab detail (thickness, reinforcement) on detail sheets, with compaction notes in spec Division 02 (Site Construction).

3

Basement Wall Design

Geotech lateral pressure values are used to design basement wall thickness and rebar. If wall is below GWL, waterproofing detail is shown on architectural sheets.

4

Retaining Walls

Geotech provides lateral pressure and passive resistance. Structural engineer designs wall thickness, reinforcement, and drainage layer (shown on site plans and detail sheets).

Changed Conditions: When Field Differs from the Report

During excavation, you may encounter soil different from what the geotech report predicted. Example: report says clay at 8 feet, but you hit sand with water at 6 feet.

This is a "changed conditions" situation:

  • Stop work at that location. Do not assume the design is still valid.
  • Notify the engineer and owner immediately. You need written direction before proceeding.
  • The engineer may: Approve continued work if conditions are still acceptable, require additional borings to understand the change, redesign foundations, or recommend dewatering.
  • Cost and schedule impact. If conditions are worse than anticipated, the contractor may be entitled to a change order for additional dewatering or redesign.

The geotech report includes a disclaimer that borings are at specific locations and soil may vary. This is why contractors take changed conditions seriously, they can cost significant time and money if not managed properly.

Common Pitfalls When Reading a Geotech Report

  • Ignoring limitations. Geotech reports always end with a limitations section. Read it. It explains that boring locations are limited, and soil may vary between borings.
  • Not checking boring locations on the site plan. Are borings clustered in one area? If the site is large and only one boring was done, soil could be very different elsewhere.
  • Assuming GWL is constant. It fluctuates. Plan for the higher level mentioned in the report.
  • Not coordinating with the structural engineer. If you see something concerning in the geotech report (low bearing capacity, high water table, clay), ask the engineer how it affects the design. Don't assume it's been accounted for.
  • Missing compaction specs in the narrative. Compaction requirements are sometimes buried in the text, not highlighted. Read carefully.

Practitioner insight

On every project, I read the limitations section of the geotech report first — not the executive summary. That section tells you where the geotechnical engineer is not standing behind their own recommendations, and that is exactly where the field surprises happen. If the limitations say ‘borings did not reach groundwater’ and your site plan shows the building footprint over the lowest part of the lot, you have a problem before you ever break ground.

— Source: Conversations with senior structural EORs and geotechnical reviewers at AHJs in California and the Pacific Northwest, synthesized from Helonic’s structural review interviews, Q1–Q2 2026.

Geotechnical Report FAQ

What is a geotechnical report?
A geotechnical report (often shortened to “geotech report” or “soil report”) is a stamped engineering document that characterizes subsurface conditions at a project site and provides foundation, excavation, and earthwork recommendations. It typically includes an executive summary, scope and methodology, boring logs, laboratory test results, recommendations for allowable bearing pressure and compaction, and conclusions. It is required by IBC Section 1803 (Geotechnical Investigations) on most U.S. commercial projects and is the basis for foundation design.
What is the difference between a geotechnical report and a soil report?
The terms are often used interchangeably. “Soil report” is the colloquial term; “geotechnical report” is the formal engineering term used in IBC, ASCE, and ASTM documents. Both refer to the same document. Some agencies (DSA in California, OSHPD for healthcare) require specific geotechnical report formats that go beyond a basic soil investigation — those have stricter requirements but the same underlying purpose.
What does a geotechnical report tell you?
A geotechnical report tells you (1) what soil and rock conditions exist below the surface at every boring location, (2) the depth to groundwater, (3) the allowable bearing pressure for foundation design, (4) compaction standards for engineered fills, (5) lateral earth pressure coefficients for retaining wall design, (6) seismic site class per ASCE 7, (7) recommendations for excavation slopes, shoring, dewatering, and over-excavation, and (8) any specific risks at the site (expansive soils, organic deposits, contamination, perched water).
How do you read a boring log?
A boring log shows soil layers at one drilled location. The vertical axis is depth (typically 0’ at top to 30’–75’ at bottom). Each horizontal band represents a soil layer with a description (“medium dense brown silty sand,” “stiff gray clay”), classification (USCS symbol like SM, CL, SP), N-value from the Standard Penetration Test (blows per foot), and water content. Most projects drill 4–12 borings across the site — you read them side by side to understand how the subsurface varies across the site.
What is the bearing capacity in a geotechnical report?
Bearing capacity is the maximum pressure the soil can sustain without excessive settlement or failure. The geotech report provides allowable bearing pressure (typically in psf or ksf) for the foundation type recommended — spread footings, mat foundations, deep foundations. Typical values: 1,500–3,000 psf for natural soils, 4,000–6,000 psf for compacted engineered fill, 10,000+ psf for rock. The structural engineer uses this value to size footings. If actual conditions don’t match the report’s assumptions (discovered during excavation), the structural engineer must redesign.
When is a geotechnical report required?
Per IBC Section 1803, a geotechnical investigation is required on most commercial projects, particularly when the site has expansive soils, liquefiable soils, slope stability concerns, or when deep foundations are anticipated. The AHJ (typically the building department) sets the local threshold — some jurisdictions require it on every project over a certain square footage; others require it only when site conditions warrant. The architect or structural engineer of record typically scopes and procures the report.
How long is a geotechnical report valid?
There is no universal expiration, but most owners and structural engineers consider a geotech report current for 2–5 years after issue. Older reports can still be valid if site conditions haven’t changed, but if there has been intervening grading, excavation, or new construction nearby, the report should be updated. Some jurisdictions (DSA, OSHPD) impose specific time limits.
What is a geotechnical report for construction vs. a geotechnical engineering report?
Both terms describe the same document. “Geotechnical report for construction” emphasizes the use case (construction permitting and design); “geotechnical engineering report” emphasizes the discipline (geotechnical engineering practice). The content and stamping requirements are identical — both are sealed by a licensed geotechnical engineer (PE) and used for foundation design and permit submittal.
MG

Manas Gandhi

Co-founder & CTO, Helonic

Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.

Areas of focus
  • AI for technical document understanding
  • Cross-discipline coordination workflows
  • Code compliance automation (IBC, NEC, NFPA, IPC, IMC, ASCE)
  • Structural and MEP drawing review systems

How this page was researched: Report structure, boring log interpretation, and code references cross-checked against IBC 2021 Section 1803 (Geotechnical Investigations), ASCE 7-22 (Seismic Site Class), ASTM D1586 (Standard Penetration Test), ASTM D2487 (Unified Soil Classification), and the geotechnical report formats accepted by DSA, OSHPD, and major U.S. city building departments. FAQ topics focused on the highest-frequency questions structural engineers and AHJs raise when reviewing geotech submittals.

Last reviewed by Manas Gandhi · May 2026

Avoid foundation surprises before the bid

Geotech reports reveal subsurface conditions early, but only if you coordinate them with structural and site drawings. Helonic helps you verify that geotech recommendations are properly reflected in construction documents.