A reviewer-grade reference for geotechnical reports (also called geotech reports or soil reports) in commercial construction: what each section contains, how to read boring logs, how bearing capacity drives footing design, and what IBC Section 1803 requires for permit submittal.
A complete geotechnical report for construction includes these sections:
Boring logs are the core of a geotech report. Each log represents a hole drilled at a specific location. Learn to read them:
The left side shows depth in feet (sometimes meters). Each horizontal band represents a soil layer. Read from top (0 ft, ground level) down.
Example: "Fill (0 to 2'), Sandy Silt (2 to 8'), Glacial Clay (8 to 25')" tells you that below the surface are three distinct layers.
Soil is described by grain size, color, consistency, and moisture. Example: "Medium dense, brown, fine-grained sand with trace mica." This description tells you:
Standard Penetration Test (SPT) is the most common field test. A weight is dropped down a tube, and resistance is measured. The result is the "N-value", recorded as "blows per foot." Example: N = 15 means 15 hammer blows to drive the sampler 1 foot.
Higher N-values mean denser, stronger soil:
The boring log shows where water was encountered. Example: "GWL at 6 feet" means the water table is 6 feet below ground level. This is critical:
The geotech engineer recommends an allowable bearing capacity (usually in PSF, pounds per square foot) for each soil layer. This is the maximum load a footing can safely support.
Example from a report: "Glacial clay below 8 feet depth: allowable bearing capacity = 3,000 PSF." The structural engineer uses this value to design footing sizes. If the bearing capacity is low, footings must be larger (and more expensive).
Column load = 300 kips (300,000 lbs). Allowable bearing = 3,000 PSF. Footing area required = 300,000 ÷ 3,000 = 100 square feet ≈ 10' × 10' footing. If bearing capacity were only 2,000 PSF, footing would need to be 15' × 15', much more expensive.
The geotechnical report will also specify depth of footing (typically 3 to 4 feet minimum to avoid frost heave and poor surface conditions).
If the project includes retaining walls, the geotech report provides lateral earth pressure values. These are used to design wall thickness and reinforcement.
Key values provided:
The geotech report will state these as coefficients (e.g., Kₐ = 0.35 for a particular soil). The structural engineer multiplies this by soil weight and wall height to calculate the total lateral load.
For fills (areas where soil is added and compacted), the geotech report specifies compaction standards. This is critical for preventing settlement.
Typical specification: "All fill shall be compacted to 95% of maximum dry density (ASTM D698) in 6-inch lifts."
What this means:
Poor compaction leads to settlement, which can crack slabs and damage structures. This is why geotech inspectors are on site during fill placement.
The groundwater level reported in the geotech investigation represents the level on the day of boring. But groundwater fluctuates with seasons, rainfall, and nearby surface water.
A good geotech report will note:
If dewatering is required, the geotech report may recommend a groundwater control system (sumps, wells, or French drains). This should be detailed in the specifications and reflected in site plans.
The structural engineer uses geotech data to design foundations:
Geotech recommends allowable bearing and minimum depth. Structural engineer calculates footing size based on column loads and specifies in footing schedule on sheet S3.
Geotech specifies fill compaction, base course, and if floor is above or below GWL. Structural engineer shows slab detail (thickness, reinforcement) on detail sheets, with compaction notes in spec Division 02 (Site Construction).
Geotech lateral pressure values are used to design basement wall thickness and rebar. If wall is below GWL, waterproofing detail is shown on architectural sheets.
Geotech provides lateral pressure and passive resistance. Structural engineer designs wall thickness, reinforcement, and drainage layer (shown on site plans and detail sheets).
During excavation, you may encounter soil different from what the geotech report predicted. Example: report says clay at 8 feet, but you hit sand with water at 6 feet.
This is a "changed conditions" situation:
The geotech report includes a disclaimer that borings are at specific locations and soil may vary. This is why contractors take changed conditions seriously, they can cost significant time and money if not managed properly.
Practitioner insight
“On every project, I read the limitations section of the geotech report first — not the executive summary. That section tells you where the geotechnical engineer is not standing behind their own recommendations, and that is exactly where the field surprises happen. If the limitations say ‘borings did not reach groundwater’ and your site plan shows the building footprint over the lowest part of the lot, you have a problem before you ever break ground.”
— Source: Conversations with senior structural EORs and geotechnical reviewers at AHJs in California and the Pacific Northwest, synthesized from Helonic’s structural review interviews, Q1–Q2 2026.
Manas is the co-founder and CTO of Helonic, where he leads engineering and AI research for construction drawing analysis. He works directly with structural, MEP, civil, and fire protection engineers to translate the way they review drawings into AI systems that flag the issues that actually matter in the field. Before Helonic, he built machine learning pipelines for technical document understanding and has spent the last several years interviewing licensed design engineers and discipline leads to ground product decisions in real practice rather than industry assumptions.
How this page was researched: Report structure, boring log interpretation, and code references cross-checked against IBC 2021 Section 1803 (Geotechnical Investigations), ASCE 7-22 (Seismic Site Class), ASTM D1586 (Standard Penetration Test), ASTM D2487 (Unified Soil Classification), and the geotechnical report formats accepted by DSA, OSHPD, and major U.S. city building departments. FAQ topics focused on the highest-frequency questions structural engineers and AHJs raise when reviewing geotech submittals.
Last reviewed by Manas Gandhi · May 2026
Related references for geotechnical, structural, and constructability review.
Understand footing and foundation details that use geotech data.
Check that geotech recommendations are reflected in structural and site plans.
Find geotechnical recommendations in Division 02 and structural divisions.
Coordinate drawings with geotech findings during preconstruction to avoid field surprises.
Handle changed conditions claims from unexpected soil conditions.
Verify that all underground utilities are coordinated with footing depths and dewatering zones.