What are the most common structural abbreviations on construction drawings?+
The most frequently used structural abbreviations are BM (beam), COL (column), FTG (footing), CONC (concrete), REINF (reinforcement), CLR (clear cover), EL (elevation), TYP (typical), TOS (top of steel), TOC (top of concrete), CIP (cast-in-place), CMU (concrete masonry unit), and SOG (slab on grade). On steel projects, AISC member callouts like W14x68 (wide flange), HSS6x6x1/4 (hollow structural section), and L4x4x3/8 (angle) function as both designation and abbreviation.
What does CLR or COVER mean in structural drawings?+
CLR (clear cover) is the distance from the outside face of concrete to the nearest face of reinforcing bar. It's a critical structural specification governed by ACI 318, typical values are 3/4 inch for slabs not exposed to earth or weather, 1-1/2 inch for beams and columns, 2 inches for concrete exposed to earth, and 3 inches for concrete cast against earth. Insufficient cover compromises fire rating, corrosion protection, and bond strength.
What does TOS, TOC, BOS mean?+
TOS (top of steel) is the finished top elevation of structural steel framing, used to dimension where decking lands. TOC (top of concrete) is the finished top elevation of a concrete slab or footing. BOS (bottom of steel or bottom of slab, context-dependent) is the bottom elevation. These appear next to elevation marks on framing plans and sections, for example 'TOS EL +12'-0"' means the top of steel at that point is at elevation +12 feet.
What are AISC steel section abbreviations?+
AISC (American Institute of Steel Construction) defines standard section designations: W = wide flange (e.g., W14x68 means 14 inches deep, 68 pounds per foot), HSS = hollow structural section (HSS6x6x1/4 = 6" square tube, 1/4" wall thickness), L = angle (L4x4x3/8 = 4" leg, 4" leg, 3/8" thickness), C = channel (C12x20.7), MC = miscellaneous channel, S = American Standard beam, WT = T-section cut from a W shape, and PL = plate (PL 1/2 = 1/2 inch plate). The full reference is the AISC Steel Construction Manual.
What is the difference between CIP, P/T, and PC concrete?+
CIP (cast-in-place) is concrete poured in formwork on-site. P/T or PT (post-tensioned) is concrete that has high-strength steel cables tensioned after the concrete cures, used for thinner long-span slabs and beams. PC (precast) is concrete manufactured off-site and erected, often pre-tensioned (PT cables tensioned before concrete pour). The abbreviation tells you where the structural element was made and how it carries load, three very different shop-drawing review processes.
Where can I find the abbreviation legend for a specific project?+
Every structural drawing set has an abbreviation legend on the general-notes sheet, typically S0.0, S0.1, or S001. That legend is the authoritative list for the project, abbreviations vary slightly between firms and structural disciplines (concrete EORs and steel EORs sometimes use different conventions). On large projects with multiple structural consultants (e.g., podium + tower), each consultant's section may have its own legend.