Reference Guide

Drawing Set Phases: SD, DD, CD, IFC, IFB

What each drawing phase contains, who it's for, and how to review documents appropriately at each phase.

Construction drawings are produced in phases, each serving a distinct purpose from design concept through construction. Understanding the phase determines what level of detail to expect, what issues are appropriate to flag, and how ready the documents are for bidding or building. Each phase has a standard abbreviation used in the industry.

SD: Schematic Design

Schematic Design is the earliest phase. The design team explores concepts, spatial layouts, and massing. SD drawings are preliminary sketches showing the architect's vision, not construction documents.

What's Shown

Conceptual floor plans and exterior elevations

Building massing and overall footprint

General area breakdowns (no detailed rooms)

Preliminary structural grid

Approximate ceiling heights

No MEP coordination yet

Who Reviews It

Owner/Client — approve design direction

Design Team — architect, engineers align on concept

City/AHJ — preliminary zoning and code check

GC/Estimators — rarely involved; too conceptual

Critical Note
SD drawings are NOT for bidding or construction. Many details change in later phases. Flag major code issues or infeasibility, but don't expect construction-level precision.

DD: Design Development

Design Development builds on Schematic Design. The design is refined, and systems (structure, MEP) are coordinated. DD is more detailed than SD but still not construction-ready.

What's Shown

Detailed floor plans with most rooms defined

Building sections and elevations

Preliminary structural framing layouts

Rough MEP routing and equipment sizes

Materials and finish selections

Detail callouts (not yet detailed)

Who Reviews It

Owner/Client — approve design and budget

Consultants — structural, MEP finalize approaches

AHJ — preliminary building permit review

GC/CM — constructability feedback (if hired early)

Why This Matters

DD is the phase where major design changes still happen affordably. If a structural approach is wrong or MEP systems clash, fixing it in DD costs much less than fixing it in CD or during construction.

CD: Construction Documents

Construction Documents are the final, complete set of drawings used for bidding and construction. Every detail, connection, and specification is documented. This is the legal and technical basis for the project.

What's Shown

Complete floor plans, elevations, sections

All structural connections and details

MEP systems fully coordinated and detailed

Finishes, hardware, and equipment schedules

Large-scale details (interior, exterior, connections)

Written specifications (CSI format)

Code compliance notes

Who Reviews It

Building Official/AHJ — full permit review

GC — creates bid estimate and schedule

Subcontractors — bid on their scope

Suppliers — order materials

Owner — final approval before construction

CD is the "legal" document set. Changes after CD are formal Change Orders. This is the appropriate phase for detailed constructability review, code compliance checking, and clash detection. See constructability review and RFI prevention.

IFC: Issued for Construction

IFC marks the moment when drawings transition from design to execution. Once IFC is stamped and signed, the set is ready for on-site use. Typically, CD and IFC are nearly identical, but sometimes minor revisions happen between them.

Status
Approved by building permit (AHJ has signed off). All plan review comments addressed.
Stamped
Architect and engineers stamp and sign each page. This is the official, legal document set.
Copies
Printed and bound for site use. Digital versions distributed to GC, subs, inspectors.
Use on Site
Subcontractors mark up IFC with field changes, RFI responses, and as-builts.

IFB: Issued for Bidding

IFB (Issued for Bidding) is the set distributed to contractors and subcontractors to prepare their bids. It's usually the same as CD or IFC, but the terminology emphasizes the purpose: contractors are pricing the work.

Contains all information needed to bid accurately
Sent to multiple contractors for competitive bidding
Includes Bid Documents: General Conditions, specifications, unit prices, schedule requirements
Questions from bidders typically addressed in an Addendum before bid due date
Becomes the basis for the Contract once a contractor is selected

Typical Drawing Phase Timeline

Here's how the phases typically flow on a project timeline:

Month 1–2: SD — Design concept approved by owner

Month 3–5: DD — Systems coordinated, budget refined, preliminary permits (if needed)

Month 6–8: CD — Full construction documents completed

Month 9: IFB distributed, contractors bid for 2–4 weeks

Month 10: Contractor selected, IFC issued, construction begins

(This timeline varies widely based on project complexity, permit requirements, and procurement schedules.)

How to Review Each Phase Appropriately

The type of feedback you provide should match the phase:

SD Review

Focus: Design intent, program fit, feasibility

Examples: Does the building meet the owner's needs? Is the structural approach sensible? Are major code violations likely?

Guidance: Focus on big-picture issues. Don't complain about missing details; they don't exist yet.

DD Review

Focus: Systems coordination, constructability, budget impact

Examples: Do MEP systems conflict with structure? Is the building method feasible? Are material choices cost-appropriate?

Guidance: This is the phase for constructability feedback. Suggest alternatives if current approach is problematic.

CD Review

Focus: Completeness, accuracy, code compliance, constructability

Examples: Are all details shown? Does electrical match the single-line? Are schedules consistent with plans? Any conflicts?

Guidance: Detailed review is appropriate here. Flag any missing information, contradictions, or code issues. This is formal review phase.

IFC/IFB Review

Focus: Bid readiness, no major changes allowed

Examples: Are all sheets current? Can bidders understand the scope? Any ambiguous areas that will generate RFIs?

Guidance: Focus on clarity and completeness. Major changes require formal Addenda. Minor clarifications can be handled in Addenda.

Common Phase-Related Issues

Watch for these mistakes:

  • Treating SD as construction documents: Expecting precision in schematic drawings. Wait for CD for detailed review.
  • Making major scope changes in CD/IFC: Large changes require reversion to DD, affecting schedule and budget. Changes after IFC are expensive.
  • Issuing IFB with unresolved plan review comments: Bidders don't know which issues are addressed. Results in RFIs and claim risk.
  • Missing the DD phase for constructability input: The best time to flag feasibility issues is DD. In CD, options are limited.
  • Not stamping IFC: Unstamped drawings aren't legal for construction. Always confirm IFC is signed by the design team.

Related Guides

Catch Phase Issues Before They Compound

Helonic's AI reviews drawings at any phase, flagging inconsistencies, missing details, and coordination issues. Catching problems early—especially during CD before bidding—prevents costly changes and RFIs.

Try Drawing Analysis